  • ANALISIS DE PRECIOS

    PARTIDA: CI-1,1DESCRIPCION DE LA PARTIDA:

    UNIDAD: SGCANTIDAD: 1.00

    RENDIMIENTO: 1.000000

    MATERIALES UND CANTIDAD COSTO TOTALSG 1 1500 1,500.00 SG 1 1500 1,500.00

    -

    -

    -

    TOTAL MATERIALES Bs.: 3,000.00 COSTO UNITARIO MATERIALES Bs.: 3,000.00

    UND CANT DEPREC. PRECIO TOTALUND 210.00 1.00 600.00 126,000.00

    MATERIALES DE PLOMERIA

    SUBESTACIN ELCTRICA PARA LA ESTACIN DE FLUJO MOR-1, DISTRITO MORICHAL DIVISIN CARABOBO

    EQUIPOS

    CONSTRUCCIN DE CAMPAMENTOS E INSTALACIONES PROVISIONALES.

    TRAILER

    MATERIALES DE ELECTRICIDAD

    UND 210.00 1.00 600.00 126,000.00 UND 420.00 1.00 100.00 42,000.00 UND 210.00 1.00 70.00 14,700.00 UND 210.00 1.00 15.00 3,150.00 UND 210.00 1.00 20.00 4,200.00

    SILLA UND 420.00 1.00 1.50 630.00 ESCRITORIO UND 420.00 1.00 1.50 630.00 COMPUTADORA UND 420.00 1.00 30.00 12,600.00

    UND 1.00 1.00 900.00 900.00 TOTAL EQUIPOS Bs.: 204,810.00

    COSTO UNITARIO EQUIPOS Bs.: 204,810.00

    CANT SALARIO TOTALCAPORAL 1.00 79.37 79.37

    6.00 79.22 475.32 1.00 79.34

    -

    TOTAL MANO DE OBRA Bs.: 554.69 651% PRESTACIONES SOCIALES 3,611.03

    -

    -

    TOTAL MANO DE OBRA DIRECTA Bs.: 4,165.72 COSTO UNITARIO DE MANO DE OBRA Bs.: 4,165.72

    COSTO DIRECTO POR UNIDAD Bs.: 211,975.72 22% ADMINISTRACION 46,634.66

    SUB TOTAL 258,610.38 14% UTILIDAD 36,205.45

    PRECIO UNITARIO Bs.: 294,815.83

    EQUPOS VARIOS

    IMPLEMENTOS DE SEGURIDAD

    CHOFEROBRERO

    CAMION 350

    MANO DE OBRA

    BAOS PORTATILES

    GASTOS MEDICOS

    COMEDORFOTOCOPIADORA

    TRAILER

  • ANALISIS DE PRECIOS

    PARTIDA: CI-1,2DESCRIPCION DE LA PARTIDA:

    UNIDAD: SGCANTIDAD: 1.00

    RENDIMIENTO: 0.500000

    MATERIALES UND CANTIDAD COSTO TOTAL

    -

    -

    -

    TOTAL MATERIALES Bs.: - COSTO UNITARIO MATERIALES Bs.: -

    UND CANT DEPREC. PRECIO TOTALUND 0.50 1.00 3,000.00 1,500.00 UND 0.50 1.00 2,900.00 1,450.00 UND 0.50 1.00 4,900.00 2,450.00

    SUBESTACIN ELCTRICA PARA LA ESTACIN DE FLUJO MOR-1, DISTRITO MORICHAL DIVISIN CARABOBO

    MOVILIZACIN

    EQUIPOSPAYLOADERRETROEXCAVADORATRACTOR D - 9 UND 0.50 1.00 4,900.00 2,450.00 COMPACTADORA DE SUELO UND 0.50 1.00 3,000.00 1,500.00 GRUA TELESCOPICA UND 0.50 1.00 3,200.00 1,600.00

    UND 5 1.00 6,000.00 30,000.00 UND 1 1.00 6,000.00 6,000.00 UND 1 1.00 800.00 800.00

    TOTAL EQUIPOS Bs.: 45,300.00 COSTO UNITARIO EQUIPOS Bs.: 90,600.00

    CANT SALARIO TOTAL5.00 79.34 396.70 1.00 79.37 79.37 3.00 79.34 79.34 6.00 79.22 475.32

    -

    -

    -

    TOTAL MANO DE OBRA Bs.: 1,030.73 651% PRESTACIONES SOCIALES 6,710.05

    -

    -

    TOTAL MANO DE OBRA DIRECTA Bs.: 7,740.78 COSTO UNITARIO DE MANO DE OBRA Bs.: 15,481.56

    COSTO DIRECTO POR UNIDAD Bs.: 106,081.56 22% ADMINISTRACION 23,337.94

    SUB TOTAL 129,419.51 14% UTILIDAD 18,118.73

    PRECIO UNITARIO Bs.: 147,538.24

    OBREROS

    TRACTOR D - 9

    OPERADOR DE EQUIPOS

    GASTOS MEDICOSIMPLEMENTOS DE SEGURIDAD

    CAMION CHUTO

    CAMIONETA PICK-UP

    MANO DE OBRA

    CAPORALCHOFER

    LOW BOY

  • ANALISIS DE PRECIOS

    PARTIDA: CI-1,3DESCRIPCION DE LA PARTIDA:

    UNIDAD: M2CANTIDAD: 500.00

    RENDIMIENTO: 500.000000

    MATERIALES UND CANTIDAD COSTO TOTALUND 0.05 6 0.30 GL 0.25 160 40.00 M2 0.02 78 1.56

    -

    -

    TOTAL MATERIALES Bs.: 41.86 COSTO UNITARIO MATERIALES Bs.: 41.86

    UND CANT DEPREC. PRECIO TOTALUND 1.00 1.00 500.00 500.00 UND 1.00 1.000 800.00 800.00

    - - - -

    SUBESTACIN ELCTRICA PARA LA ESTACIN DE FLUJO MOR-1, DISTRITO MORICHAL DIVISIN CARABOBO

    REPLANTEO Y NIVELACIN.

    ESTACAPINTURACINTA REFLECTIVA

    EQUIPOSEQUIPO DE TOPOGRAFIACAMIONETA PICK-UP

    - - - -

    - -

    -

    TOTAL EQUIPOS Bs.: 1,300.00 COSTO UNITARIO EQUIPOS Bs.: 2.60

    CANT SALARIO TOTAL1.00 220.00 220.00 1.00 79.22 79.22 1.00 79.34 79.34

    -

    -

    -

    -

    TOTAL MANO DE OBRA Bs.: 378.56 651% PRESTACIONES SOCIALES 2,464.43

    -

    -

    TOTAL MANO DE OBRA DIRECTA Bs.: 2,842.99 COSTO UNITARIO DE MANO DE OBRA Bs.: 5.69

    COSTO DIRECTO POR UNIDAD Bs.: 50.15 22% ADMINISTRACION 11.03

    SUB TOTAL 61.18 14% UTILIDAD 8.56

    PRECIO UNITARIO Bs.: 69.74

    MANO DE OBRATOPOGRAFO

    GASTOS MEDICOS

    IMPLEMENTOS DE SEGURIDAD

    CHOFER AYUDANTE DE TOPOGRAFO

  • ANALISIS DE PRECIOS

    PARTIDA: CI-1,4DESCRIPCION DE LA PARTIDA:

    UNIDAD: SGCANTIDAD: 1.00

    RENDIMIENTO: 0.500000

    MATERIALES UND CANTIDAD COSTO TOTAL

    -

    -

    -

    -

    TOTAL MATERIALES Bs.: - COSTO UNITARIO MATERIALES Bs.: -

    UND CANT DEPREC. PRECIO TOTALUND 0.50 1.00 3,000.00 1,500.00 UND 0.50 1.00 2,900.00 1,450.00

    SUBESTACIN ELCTRICA PARA LA ESTACIN DE FLUJO MOR-1, DISTRITO MORICHAL DIVISIN CARABOBO

    DESMOVILIZACIN

    EQUIPOSPAYLOADERRETROEXCAVADORA UND 0.50 1.00 2,900.00 1,450.00

    UND 0.50 1.00 4,900.00 2,450.00 COMPACTADORA DE SUELO UND 0.50 1.00 3,000.00 1,500.00 GRUA TELESCOPICA UND 0.50 1.00 3,200.00 1,600.00

    UND 5 1.00 6,000.00 30,000.00 UND 1 1.00 800.00 800.00

    -

    TOTAL EQUIPOS Bs.: 39,300.00 COSTO UNITARIO EQUIPOS Bs.: 78,600.00

    CANT SALARIO TOTAL5.00 79.34 396.70 1.00 79.37 79.37 3.00 79.34 79.34 6.00 79.22 475.32

    -

    -

    TOTAL MANO DE OBRA Bs.: 1,030.73 651% PRESTACIONES SOCIALES 6,710.05

    -

    -

    TOTAL MANO DE OBRA DIRECTA Bs.: 7,740.78 COSTO UNITARIO DE MANO DE OBRA Bs.: 15,481.56

    COSTO DIRECTO POR UNIDAD Bs.: 94,081.56 22% ADMINISTRACION 20,697.94

    SUB TOTAL 114,779.51 14% UTILIDAD 16,069.13

    PRECIO UNITARIO Bs.: 130,848.64

    MANO DE OBRAOPERADOR DE EQUIPOSCAPORAL

    RETROEXCAVADORA

    CAMION CHUTOCAMIONETA PICK-UP

    TRACTOR D - 9

    GASTOS MEDICOSIMPLEMENTOS DE SEGURIDAD

    CHOFER OBREROS

  • ANALISIS DE PRECIOS

    PARTIDA: CI-1,5DESCRIPCION DE LA PARTIDA:

    UNIDAD: MLCANTIDAD: 145.00

    RENDIMIENTO: 70.000000

    MATERIALES UND CANTIDAD COSTO TOTAL

    -

    -

    -

    TOTAL MATERIALES Bs.: - COSTO UNITARIO MATERIALES Bs.: -

    UND CANT DEPREC. PRECIO TOTALUND 1.00 1.00 1,200.00 1,200.00 UND 1.00 1.000 300.00 300.00

    SUBESTACIN ELCTRICA PARA LA ESTACIN DE FLUJO MOR-1, DISTRITO MORICHAL DIVISIN CARABOBO

    DEMOLICIN DE CERCA DE CICLN CON BROCAL, INCLUYECARGA Y BOTE DEL MATERIAL PRODUCTO DE LA DEMOLICIN

    EQUIPOSCAMION VOLTEOEQUIPOS VARIOS UND 1.00 1.000 300.00 300.00

    UND 1.00 1.00 3,000.00 3,000.00 - -

    -

    TOTAL EQUIPOS Bs.: 4,500.00 COSTO UNITARIO EQUIPOS Bs.: 64.29

    CANT SALARIO TOTAL0.25 79.37 19.84 1.00 79.34 79.34 1.00 79.34 79.34 6.00 79.22 475.32

    -

    -

    -

    TOTAL MANO DE OBRA Bs.: 653.84 651% PRESTACIONES SOCIALES 4,256.51

    -

    -

    TOTAL MANO DE OBRA DIRECTA Bs.: 4,910.36 COSTO UNITARIO DE MANO DE OBRA Bs.: 70.15

    COSTO DIRECTO POR UNIDAD Bs.: 134.43 22% ADMINISTRACION 29.58

    SUB TOTAL 164.01 14% UTILIDAD 22.96

    PRECIO UNITARIO Bs.: 186.97

    MANO DE OBRACAPORAL

    EQUIPOS VARIOSPAYLOADER

    GASTOS MEDICOS

    IMPLEMENTOS DE SEGURIDAD

    CHOFEROBRERO

    OPERADOR DE EQUIPO

  • ANALISIS DE PRECIOS

    PARTIDA: CI-1,6DESCRIPCION DE LA PARTIDA:

    UNIDAD: MLCANTIDAD: 70.00

    RENDIMIENTO: 47.000000

    MATERIALES UND CANTIDAD COSTO TOTALKG 0.25 25 6.25

    UND 0.5 30 15.00 UND 0.5 20 10.00 SG 1 150 150.00

    -

    TOTAL MATERIALES Bs.: 181.25 COSTO UNITARIO MATERIALES Bs.: 181.25

    UND CANT DEPREC. PRECIO TOTALUND 1.00 1.00 3,200.00 3,200.00 UND 1.00 1.00 6,000.00 6,000.00

    EQUIPOSGRUA TELESCOPICACAMION CHUTO

    SUBESTACIN ELCTRICA PARA LA ESTACIN DE FLUJO MOR-1, DISTRITO MORICHAL DIVISIN CARABOBO

    REUBICACIN DE TUBERA DE 2" EXISTENTE EN EL SITIO

    ELECTRODODISCO ESMERILCEPILLO DE ALAMBREMATERIALES VARIOS

    UND 1.00 1.00 6,000.00 6,000.00 UND 1.00 1.00 300.00 300.00 UND 1.00 1.00 250.00 250.00

    -

    TOTAL EQUIPOS Bs.: 9,750.00 COSTO UNITARIO EQUIPOS Bs.: 207.45

    CANT SALARIO TOTAL0.25 79.37 19.84 4.00 79.22 316.88 4.00 79.34 317.36 1.00 79.34 79.34 1.00 79.22 79.22 3.00 79.34 238.02

    -

    TOTAL MANO DE OBRA Bs.: 1,050.66 651% PRESTACIONES SOCIALES 6,839.81

    -

    -

    TOTAL MANO DE OBRA DIRECTA Bs.: 7,890.48 COSTO UNITARIO DE MANO DE OBRA Bs.: 167.88

    COSTO DIRECTO POR UNIDAD Bs.: 556.58 22% ADMINISTRACION 122.45

    SUB TOTAL 679.03 14% UTILIDAD 95.06

    PRECIO UNITARIO Bs.: 774.09

    IMPLEMENTOS DE SEGURIDAD

    MANO D...